Document: Reference Guide - Table of Contents Document: How to Use the Reference Guide Document: End of Period [U04] Overview (main document) Website: www.mccue.com



End of Period [U04]: Overview

In This Document


In Related Documents

 


Introduction

EOP is a group of updates and reports, executed automatically in a batch (non-interactive) environment. EOP is executed separately for each portfolio. All interactive updating (i.e., data entry) for the portfolio is prohibited while EOP is processing.

A normal EOP process is composed of several steps:

  1. EOP is submitted to a batch queue for later execution by a designated LeasePak operator at the close of the day, month and/or year, using the Submit update [U0401].

  2. Data files and other applicable files are backed up by a system operator.

  3. The administrator will usually have set EOP to begin processing after backups are completed. EOP automatically submits a batch job for each of the modules (updating/reporting) scheduled to perform. These batch jobs may be executed in parallel to better use the system’s resources.

    Note: Data file backups must be synchronized to be performed only when daily updating for all portfolios is complete.

Reports are created separately for each portfolio. Completion of the entire EOP process is not dependent on other portfolios (e.g., if one EOP terminates abnormally, others may complete successfully, assuming the same problem does not exist in other portfolios).

The elapsed execution time of all EOP processes for the entire database may decrease if each portfolio is assigned a separate EOP batch queue, thus allowing each portfolios to execute its EOP processes simultaneously.

 

Document: Reference Guide - Table of Contents Document: How to Use the Reference Guide Top of Current Document Document: End of Period [U04] Overview (main document)

Location: End of Period [U04] Overview - Introduction Topic: EOP Module List Topic: EOP Batch Jobs Topic: EOP Dependencies Topic: EOP Multiple Processes
Topic: EOP Queue Priority Topic: EOP Module Status Definitions EOP Update: End of Period Start [U0410] EOP Update: End of Period End [U0499]

Module List

This section summarizes the EOP modules. It may be used as a reference list of all EOP modules, or to determine the effects of skipping/restarting a specific module.

EOP modules in the following list are shown in order of execution. That is, the modules are executed in this order if EOP is executed sequentially. With sequential execution, only one module executes at a time. The previous module must complete before the next module may begin. If modules are executed in parallel, execution and completion of modules may change because certain modules may execute earlier if they are not dependent on any as yet uncompleted modules.

To summarize, when executing EOP sequentially, the priority is used to determine which module to execute next. When executing EOP in parallel, both the priority and module dependencies are used to determine which module(s) to execute next.

For each module, the following items are listed:

 

EOP Module List (In order of Execution)

EOP MODULE

NUMBER

GROUP

UPD

EOP ONLY

SKIP INSTRUCTIONS

EOP Start

U0410

Any

 

YES

Do not skip unless ALL modules of EOP are also skipped.

Batch Assessments

U0418

Day

*

YES

 

Vertex Interface

U0437

Day

*

YES

 

Cycle Accruals

U0301

Acc

*

 

If skipped, also skip Cycle Invoices [U0302] and Cycle Invoices (Formatting) [U0457].

Automatic Lease Extension

U0430

Day

*

YES

 

Notes Payable Accrual

U0905

Day

*

 

If skipped, note outstanding balances and calculated interest amounts are not updated for the current month.

Sequential Updates

U0411

Day

*

YES

If skipped, also skip Sequential Updates Post- processor [U0412]

o Batch Payments - Seq Upd

U0415

Day

*

YES

 

o Auto Susp Income - Seq Upd

U0439

Day

*

YES

 

o Auto Charge Off - Seq Upd

U0440

Day

*

YES

 

o Maturing Lease Init - Seq Upd

U0431

Day

   

o Collateral Init - Seq Upd

U0432

Day

   

o Vendor Totals - Seq Upd

U0441

Month

   

o Portfolio Status - Seq Upd

U0442

Month

   

o Depreciation - Seq Upd

U0443

Month

   

o ITC Accrual - Seq Upd

U0444

Month

   

o Missing Aux Elem - Seq Upd

U0445

Month

   

o Late Charges - Seq Upd

U0433

Month

   

o Cycle Invoices -Seq Upd

U0302

Inv

*

 

If skipped, also skip Cycle Invoices (Formatting) [U0457].

o Assumed Payments - Seq Upd

U0414

Day

*

YES

 

o Preauth Payments - Seq Upd

U0304

Day

*

  

Sequential Updates Post-processor

U0412

Day

*

YES

Do not skip unless the Sequential Updates [U0411] is also skipped.

Sequential Updates Post-merge

U0413

Day

*

YES

Do not skip unless the Sequential Updates [U0411] is also skipped.

Cycle Invoices (Formatting)

U0457

Inv

*

  

Vendor ACH

U0424

Day

*

YES

 

Vendor Income Participation

R0801

Month

*

  

Vendor Payment Participation

R0805

Month

*

 

Do not skip unless all End of Month modules are also skipped.

Investor Income Participation

R0701

Month

*

  

Investor Settlement

U0124

Day

*

  

Use Tax Disbursal

U0449

Month

*

YES

 

Cashier’s Check Disbursal

U0117

Day

*

  

Loan Accrual

U0455

Month

*

YES

 

Maintenance Report

U0416

Day

 

YES

 

General Ledger Reconciliation

R0403

Month

   

Trial Balance

R0901

Month

   

Accounts Receivable Balancing

R0404

Month

   

Income Receivable Balancing

R0407

Month

   

Accounts Payable Balancing

R0408

Month

   

Cash Receipts Journal

R0411

Month

   

Assessments Receivable Aging

R0607

Month

   

Vendor Delinquency

R0603

Month

   

Off Lease Inventory

R1001

Month

   

Suspense Review

R0203

Day

*

  

Insurance Status Update

U0421

Day

*

YES

 

New Lease Earnings

R0101

Month

   

Accounts Balances

R0103

Month

   

Book Gain/Loss

R0108

Month

   

Operator’s Status Review

R0202

Month

   

Salesperson Commission

R0204

Month

   

Turnaround Timing

R0503

Day

   

Delinquency

R0601

Month

   

Lease Inventory

R0902

Month

   

Certificate of Ownership

R0903

Month

   

Insurance Follow-Up

R0904

Month

   

Paid Off Leases

R0912

Month

   

Portfolio Status

R0104

Month

   

Taxable Income

R0301

Month

   

Tax Depreciation

R0304

Month

   

Investment Tax Credit Listing

R0302

Month

   

Investment Tax Credit Review

R0303

Month

   

Energy Tax Credit Listing

R0307

Month

   

Energy Tax Credit Review

R0308

Month

   

Daily Transaction Journal

R0405

Day

   

Notes Transaction Journal

R1205

Day

   

Monthly Transaction Journal

U0456

Month

   

Monthly Notes Transaction Journal

R1205

Month

   

General Ledger Entries Listing

R0406

Day

   

Rental Income

R0409

Month

   

G/L Interface to In-House System

U1003

Day

*

YES

If skipped, also skip Zero Daily General Ledger Accounts update [U0422].

Zero Daily General Ledger Accounts

U0422

Day

*

YES

 

Zero Monthly G/L Account

U0450

Month

*

YES

 

Historical General Ledger

R0410

Month

   

Application Activity Log

R0501

Day

   

New Lease Letters

U0417

Day

*

YES

 

Monthly Application Summary

R0507

Month

   

Insurance Tracking

U1002

Month

*

  

Closed Lease Cleanup

U0419

Day

*

YES

 

Vendor File Cleanup

U0423

Month

*

YES

 

Historical Payment/DTX Cleanup

U0451

Month

*

YES

 

Lease Level Trans DTY Cleanup

U0452

(no longer needed)

(appropriate transactions are generated at lease level)

Application File Cleanup

U0453

Month

*

YES

 

Year End File Build

U0481

Year

*

YES

Do not skip unless all End of Month modules are also skipped. If skipped, also skip all End of Year reports ([U0603], [U0604], [U0606], [U0607], [U0483], and [U0484]) and the Clear Year to Date Fields update [U0482].

Investment Tax Credit Listing (EOY)

U0603

Year

  

Skip if the Year End File Build update [U0481] is skipped.

ITC Review (EOY)

U0604

Year

  

Skip if the Year End File Build update [U0481] is skipped.

Depreciation (EOY)

U0606

Year

  

Skip if the Year End File Build update [U0481] is skipped.

Gain / Loss (EOY)

U0607

Year

  

Skip if the Year End File Build update [U0481] is skipped.

Energy Tax Credit Listing (EOY)

U0483

Year

  

Skip if the Year End File Build update [U0481] is skipped.

Energy Tax Credit Review (EOY)

U0484

Year

  

Skip if the Year End File Build update [U0481] is skipped.

Zero Monthly G/L Accounts (EOY)

U0450

Year

*

 

Skip if the Year End File Build update [U0481] is skipped.

Clear Year to Date Fields

U0482

Year

*

YES

Skip if the Year End File Build update [U0481] is skipped.

EOP End

U0499

Any

*

YES

Skip only if EOP Start is skipped.

 

Document: Reference Guide - Table of Contents Document: How to Use the Reference Guide Top of Current Document Document: End of Period [U04] Overview (main document)

Location: End of Period [U04] Overview - Introduction Topic: EOP Module List Topic: EOP Batch Jobs Topic: EOP Dependencies Topic: EOP Multiple Processes
Topic: EOP Queue Priority Topic: EOP Module Status Definitions EOP Update: End of Period Start [U0410] EOP Update: End of Period End [U0499]

Batch Jobs


Each module of EOP (e.g., Accruals, Maintenance Report, Trial Balance, etc.) is its own batch job. Therefore, a large number of batch jobs is produced and queued to the specified EOP batch queue. For this reason, a batch queue separate from the system batch queue (SYS$BATCH) should be set up for each portfolio’s EOP process. This avoids clogging the system batch queue with EOP jobs.

 


Dependencies


There is a precise order in which each EOP module is executed. All General Ledger updating, for example, must be performed before the Daily Transaction Journal is created, so that the transaction journal for the day will be complete. This would seem to indicate that modules must be executed in sequence, each module waiting for the previous one to complete before starting. This may not be the case, however.

Several modules may be executed in parallel if they are not dependent on any other modules which are currently executing or are waiting to be executed. Executing in parallel means that several modules may execute at the same time, thereby more effectively using computer resources. Dependencies refer to relationships between modules. For example, a module is dependent on another module if it must use data that the other is generating or, conversely, if it must clear or delete data that the other is using. In the example in the previous paragraph, the Daily Transaction Journal is dependent on programs which update the General Ledger (e.g., Accrual update).

Dependencies define "parent-child" relationships between modules. Module 1 is a parent to module 2 if it must complete before module 2 may begin. Module 1 is not a parent to module 2 if it has no relationship or bearing on processing module 2. For example, the Accrual update [U0301] is a parent

to the Daily Transaction Journal [R0405], because the Accrual update may produce General Ledger transactions that must be reported on the Daily Transaction Journal. Module 2 is a "child" of module 1 if module 2 must wait for module 1 to complete before it may begin. Using the same example, the Daily Transaction Journal is a child of the Accrual update.

Parent-child relationships determine the modules which may be executed in parallel. Again using the above example, the Accrual update and the Maintenance report, which do not depend on each other, may execute at the same time, while the Daily Transaction Journal must wait for the Accrual update to complete before it may begin.

EOP determines the parent-child relationships between all modules and automatically determines which modules may execute and which modules must wait. For the modules which must wait, EOP automatically monitors them and starts them when their parents are complete.

 

Document: Reference Guide - Table of Contents Document: How to Use the Reference Guide Top of Current Document Document: End of Period [U04] Overview (main document)

Location: End of Period [U04] Overview - Introduction Topic: EOP Module List Topic: EOP Batch Jobs Topic: EOP Dependencies Topic: EOP Multiple Processes
Topic: EOP Queue Priority Topic: EOP Module Status Definitions EOP Update: End of Period Start [U0410] EOP Update: End of Period End [U0499]

Multiple Processes


In certain cases, it may be beneficial to split the processing of updates into multiple processes. That is, instead of executing an update once for the portfolio, it may be slated to execute several times, each time processing a different set of leases in the portfolio. These separate jobs may then execute in parallel, thereby more fully using the computer’s capabilities.The Sequential Updates Post Processor [U0412] and Sequential Updates Post Merge [U0413] then consolidate results of parallel processing.

Multiple process is available only for the Sequential update [U0411] of EOP. This update performs many varied tasks, and uses the bulk of the processing time required by EOP.

There are performance trade-offs when executing multiple processes rather than a single process. Analysis of the portfolio should be performed by an MSI representative before using this multiple processing capability of LeasePak.

 


EOP Queue Priority


LeasePak automatically adjusts the priority at which certain EOP modules are executed. The following modules are not adjusted; they run at whatever priority assigned them for the EOP queue:

Refer to the module list above for standard priorities. All other modules execute at the EOP queue priority for the first 3 to 6 CPU seconds and then have their priority lowered by 1 (if the EOP queue has a priority greater than 1). This allows the more critical EOP jobs to run faster.

If other low priority jobs are to be executed simultaneously with the EOP process, it may therefore be advisable to increase the EOP queue priority by 1.


Document: Reference Guide - Table of Contents Document: How to Use the Reference Guide Top of Current Document Document: End of Period [U04] Overview (main document)

Location: End of Period [U04] Overview - Introduction Topic: EOP Module List Topic: EOP Batch Jobs Topic: EOP Dependencies Topic: EOP Multiple Processes
Topic: EOP Queue Priority Topic: EOP Module Status Definitions EOP Update: End of Period Start [U0410] EOP Update: End of Period End [U0499]

Module Status Definitions


This section describes EOP module statuses in more detail. It may be used as a reference for any update or report which shows module statuses (e.g., the EOP Status Review report [U0402] or the Halt/Restart/Skip update [U0404]).

Each module of EOP has a current status associated with it. The status indicates that the module has completed successfully, is currently executing or waiting to execute, or has started executing and stopped without completing. The status assists in determining if the EOP process has completed successfully or if some intervention is required in order to allow it to complete.

EOP statuses are:

 


End of Period Start [U0410]

This module performs the following:

When End of Period is submitted by the LeasePak operator using the Submit update [U0401], a single job is placed on the End of Period batch queue. This batch job, when released, executes the End of Period Start module. The End of Period Start module queues all the other End of Period modules to the batch queue.

Skip Comments: This module should not be skipped unless all of the End of Period is also skipped.

 

Document: Reference Guide - Table of Contents Document: How to Use the Reference Guide Top of Current Document Document: End of Period [U04] Overview (main document)

Location: End of Period [U04] Overview - Introduction Topic: EOP Module List Topic: EOP Batch Jobs Topic: EOP Dependencies Topic: EOP Multiple Processes
Topic: EOP Queue Priority Topic: EOP Module Status Definitions EOP Update: End of Period Start [U0410] EOP Update: End of Period End [U0499]

End of Period End [U0499]

This module completes the End of Period process by:

Refer to the CCA Accrual update [U1501] for more information.

Skip Comments: The End of Period End module [U0499] may be skipped only if End of Period Start [U0410] is skipped (that is, it may not be skipped by itself). If this module is skipped, updates are unlocked but the next execution dates are unchanged.

To skip execution of the Collection module after the Collection initialization program has already begun execution:

 

© 2001 by McCue Systems Incorporated.
All rights reserved.

The information contained in this document is the property of McCue Systems, Inc. Use of the information contained herein is restricted. Conditions of use are subject to change without notice. McCue Systems, Inc. assumes no liability for any inaccuracy that may appear in this document; the contents of this document do not constitute a promise or warranty. The software described in this document is furnished under license and may be used or copied only in accordance with the terms of said license. Unauthorized use, alteration, or reproduction of this document without the written consent of McCue Systems, Inc. is prohibited.


Document: Reference Guide - Table of Contents Document: How to Use the Reference Guide Top of Current Document Document: End of Period [U04] Overview (main document)